Timeline

  • Submittal of the CUP (Conditional Use Permit) on 3/1/2012
  • - CUP Contingent Item # 1   Development of Master Plan on 3/1/2012
  • - CUP Contingent Item # 2   Civil Drawings on 3/1/2012
  • - CUP Contingent Item # 3   Storm Water Design on 3/1/2012
  • - CUP Contingent Item # 4   Wetland and Buffer Calculations on 3/1/2012
  • - CUP Contingent Item # 5   Architectural Elevations on 3/1/2012
  • - CUP Contingent Item # 6   Landscaping Plans on 3/1/2012
  • - CUP Contingent Item # 7   Parking Plans on 3/1/2012
  • - CUP Contingent Item # 8   Traffic Study on 3/1/2012
  • - CUP Contingent Item # 9   GEO Tech Report on 3/1/2012
  • Building Permit (BP) Submittal in the Summer of 2013 on 8/1/2013
  • - BP Contingent Item #1 Architectural Drawings on 8/1/2013
  • - BP Contingent Item #2 Engineering Calculations on 8/1/2013
  • Building Construction starting Summer of 2014 on 8/1/2014
  • - Site Work on 8/1/2014
  • - Building Shell on 8/1/2014
  • - TI’s – Interiors and Furniture on 8/1/2014
  • - Complete Site Mitigation on 8/1/2014
  • - Building Inspection and Final! on 12/1/2015
 